This project is a 4-phase, $3.1 million (M+E), 11,000 m2 complete upgrade of all mechanical and electrical infrastructure, as well as substantial renovations. London Hydro was approached regarding this project and the design was coordinated to minimize downtime and costs to the owner. A new pad mounted transformer will be provided to suit the planned renovations. London Hydro has planned on cutting into the existing u/g primary cables and to locate a new pad adjacent to the existing. The main distribution equipment within the building will be completely replaced to suit the planned renovation work.
Size:
11,000 m2
Location:
London, ON
Client:
Cornerstone Architecture Inc.
Year Completed:
2014